Oranjemund Online

ORANJEMUND DISCUSSIONS! => Oranjemund Bush Telegraph! => Topic started by: Mike Stenson (RIP) on November 21, 2008, 02:16:06 PM

Title: Namdeb shutting down production for a month
Post by: Mike Stenson (RIP) on November 21, 2008, 02:16:06 PM
Just heard Namdeb is shutting down production from the 16/12/2008 to 15/01/2009.
Most employees will have to take leave, going to be a very quiet Chrismas here in Oranjemund.  image031
Details will be be briefed to employees next week.
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on November 21, 2008, 06:09:49 PM
A long Christmas holiday ... our factory , and in fact a lot of concerns  used to do annual shutdown from  about 18 Dec till about 11 Jan  ... a whole month is however long .. ... reasons for this .. anyone in the know ??
Title: Re: Namdeb shutting down production for a month
Post by: Bertie Horak on November 22, 2008, 03:57:38 AM
I do not understand how a forced holiday can save a company money, don't the employees get salaries anyway? and production will drop? ... maybe somebody can explain it to me... totally out of my field and I've never worked for a company before.  I can only see that a company would save if running costs are higher than their "harvest".
I also heard that the De Beers pensioners got letters that they will not be getting an increase in pension in January, and also no end of year bonus at the end of the month as usual.. simply not enough funds.  They are however getting an increase of 6,x% this month???  Maybe somebody can enlighten me?
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on November 22, 2008, 05:44:59 AM
The mine has massive stockpiles both of material at the plants and their stockpile of diamonds is ever increasing, yet they are unable to sell it due to the world financial crises, it makes economical sense not to carry on making that stockpile larger if you cannot sell it....kinda like baking a loaf of bread for a family of four, the bread is half eaten , yet you bake another one.....and then another one....the family is still living and going through the motions , yet they do not need all the bread.... running costs to the mine will be in the fact that their are no vast fuel bills to pay, certain sections of the mine will be shut down, thus saving on electrical bills, no overtime to paid, a huge reduction on a workforce to fees...... reduction on leave that might have had to be paid out in case of future retrenchments........

Thats how I see it....

From Spar's perspective, it will be devastating, although we were expecting a longer shutdown, we are still hoping that due to economic circumstances, most of the "holiday" people plan to stay in this quiet town for their holiday, thereby shopping local......

From my perspective, which is very unbusinesslike (i made that word up) , I look forward to seeing the town empty....... I get a kick outta it...... quiet, alone, the braai's feel different.... the beach quieter....in a sense.....you get to see who the real Oranjemunders are.....

Title: Re: Namdeb shutting down production for a month
Post by: SandyB on November 22, 2008, 05:54:15 AM
Thanks for that .. thought it  would have had  something to do with economic  slowdown ... and yes  as in the case of the mine there is a saving in running cost ..   and yes   we have done so in the past as  well ..  but you can only bank on  building up so much stock ..   we done that before .. our bread bag, salt packaging , and  fresh produce commodity sizes ..  we have run during  the deathly quiet times  banking on the orders comin in later .. but even that party  stops .. then we  shut down and maintain  and send  people on leave ...
Title: Re: Namdeb shutting down production for a month
Post by: Michele Alexander (Voden) on November 22, 2008, 07:11:40 AM
Trying times ahead indeed, one can't help but wonder is this the start of the next Great Depression? I've had a couple of wives wondering how they are going to manage without their husband's standby/overtime, especially at this time of year.
Unfortunately Namdeb has been in the habit of paying their staff their Dec wages a couple of days before Christmas and so by the time the middle of Jan comes around a lot of the employees have no money left - just when they need to be buying school uniforms and stationery for the new school year. Surely it would have been better to hold back their annual bonus that is paid at the end of November and rather pay this out just before Christmas and leave their normal salary for the end of Dec?
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on November 22, 2008, 07:18:36 AM
 Michele   so correct ..   first one ..  never budget based on  overtime and standby ... its  not  garuanteed .. next the bonus ..  put  most of it away  after  doing a bit of treating ,,  and yes the mid   January depression .. I see people repeating it over and over again ... been there once or twice  in my life and resolved to  stop repetition .. its not nice ... thats why I hung onto my Opel  for 11 years ...   cos  after  60 months I was debt free and  only had to  pay for routine maintenance ... 
Title: Re: Namdeb shutting down production for a month
Post by: Michele Alexander (Voden) on November 22, 2008, 07:25:57 AM
Sandy - I wish more people would think like you do but unfortunately they don't - they just see the money in their bank account and have to spend it. I also paid off both our cars as soon as possible and although I would love to buy a bigger one to accommodate baby no. 3 I also know that it just doesn't make sense and that my little mom's taxi will do us fine around town.

From Spar's point of view I think this is going to be our worst Christmas to date but I'm hoping that the others will have listened to my warnings of having to decrease orders and only order the necessities. 
Title: Re: Namdeb shutting down production for a month
Post by: Mike Stenson (RIP) on December 09, 2008, 02:24:51 PM
We got briefed by the GM today.
Namdeb has to cut costs by 50%.
The workforce will also be cut by 50%.
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on December 09, 2008, 06:53:26 PM
Although we have work trickling in for the new year .. the loading does not look fantastic .  some of our opposition are closing  for full month 12th  to  12th ...  we lucky we still  have  workload  .. I'm now starting to  produce some  orders for early january .. but then  it looks like a dry-up ... our official holiday is from  19th till 5th .. I have now been asked to  give entire staff  extra leave till 12th .. I'm standing fast  and have said i will only  give to selected  people with  excess leave .. and definitely a  want crew in to do essential maintenance  issues that have been  screaming at me for a good part of the year  and to  keep  one or two key machines  clear of   any backlog .. .. If I dont  do them then .. the I will be pushing machines  to limits ...  I  am taking the optimistic angle that yes work will come in .. and  also  that we will be up to speed to accomodate  new business  from  existing  and  new customers maybe frustrated by their current  vendors inability  to deliver .. we  won the lucrative Babysoft range   under similar circumstances  a couple of years ago by being ready   and raring to help .. so  Right now I'm like the lone messenger but yes sticking to my guns ..  and  yes  slowly winning  by  persistence in my stance ..
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on December 09, 2008, 07:09:20 PM
I still wonder if people will be emptying out of the town for the Xmas period or will they be hanging about, perhaps uncertain of their future?

Title: Re: Namdeb shutting down production for a month
Post by: SandyB on December 09, 2008, 07:20:43 PM
Mmm Mikes eyes doing the  proverbial  ... wondering.. yes we all wondering ...  like said I'm pitching optimistic .. and yes been through lean times before .. all its done for me is  allowed me to consolidate and  get out of the  runaway train  feeling as happens in a production environment  and develop a focus  and  yes get closer to my employees as they needed my   ecouragement and positive input .. .. but yes different for each sector ... during our lean time  3 years ago we just learnt to  work more  smartly   plan more cleverly .. and yes  wait for the  boom  time that occured  6 months down the line .. we all stuck together through that time and when it was over  .. i could say .. " see it was'nt that bad  see what  we  can do ?? "  but yes running a supermarket and having  loss of income for too many months can wreak havoc on  your business and personal plans ..   Guys lets all just hold  thumbs and be the optimists  . and  get strength form the adversity thrown at us ...
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on December 10, 2008, 07:37:27 PM
Seems like my pitching  optimistic is  creating good energy ...  firstly .. I took a close look at planning board and looked at  completion dates  for tonnage required  by phase ,, 1 year end ,,, 2  early January ..  the planner was in my opinion cutting it so fine  not taking inot account   shutting down  on weekends .. we had a disastrous startup this monday after a  month and half of  continious run  and  fantastic  efficiencies ..    this week was the dark side of the mirror ..  awfull  .. awfull ...  so did my own  little   number ..  tonnage by  machine ..  days  required  to do it safely ..  plus factoring in   tings going wrong .. into  the new year ... it was a case of balancing on sword edge .. furthermore ..  quick cost of excess wastage  and  productive time lost ...   big bucks .. the overtime bill would   pale into  total insignificance compared .. i put it out all  neatly   by machine and  requirements and painted the potential for doom and disapointed customers as well ...  so i got  open book to run right through  to  shutdown  on  thursday ..   the moment  I got that right ...  manna dropped from heaven ..   more work has flowed in ..  regular  customers .. booking ahead ...   so far from   nil for first week in Jan ... to  2 weeks on 3  key machines ... see  think positive  ..   do certain  actions .. and the rest follows ...  If it does not follow that way  .. then it was meant to be  .. then you  make other plans ..   a lesson for all ..
Title: Re: Namdeb shutting down production for a month
Post by: Leon Sumter on December 14, 2008, 05:00:53 PM
50 % of the workforce ! That's a lot of people who will be looking for alternative employment. My heart goes out to them. The economy is very depressed at the moment and lots of big and small companies are laying off people now, what with the whole US subprime debacle spreading all over the world.
Leon
Title: Re: Namdeb shutting down production for a month
Post by: David John Long on December 14, 2008, 06:53:43 PM
Dunno if this was mentioned some where else on the site, but it seems Debeers Marine Nam is also pulling up anchors and stopping production for 2 months... Guess I don;t need to bother coming back from NZ then :)
Title: Re: Namdeb shutting down production for a month
Post by: Leon Sumter on December 16, 2008, 08:26:01 PM
Hi Mike
Did the GM give any timeline as to when the Namdeb workforce is to be cut by 50%?
Title: Re: Namdeb shutting down production for a month
Post by: Andrew Darné on December 16, 2008, 10:39:18 PM
Another oppurtunity has opened to apply for Voluntary Separation from Tuesday 9 December until 16 February 2009. Quite a big chance. I reckon there will be a huge number of folk applying now. 50% is a fat wack of people that must go.

Ouch... but we will see what happens after New Years...
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on December 17, 2008, 06:50:03 AM
Time  flies ..  me  been so busy .. work  and yes   the social ..   today is the 17th .. did the  shutdown occur on the  12th ?? 
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on December 17, 2008, 08:48:59 AM
JOHANNESBURG (miningweekly.com) – Namibian diamond producer Namdeb and De Beers Marine Namibia would immediately reduce production for the remainder of 2008 and early 2009, as a result of high inventory levels and low liquidity impacting on wholesale clients' ability to purchase new rough diamond supplies.

Namdeb said in a statement on Friday that prices for polished diamonds remained above the levels seen at the beginning of the year, however, the wholesale market for new rough diamonds in the major cutting centres had been impacted on by the global economic crisis.

The companies would reduce production in line with demand and would try to preserve cash.

For De Beers Marine Namibia this would mean that the vessels would be laid up in port from mid-December until early in 2009.

The producer said it would strive to reduce the impact on its employees, however, a reduction in staff was inevitable.

Namdeb would reduce some mine sites to one shift and stopping most operations over the festive season, and others would carry out more essential maintenance. 

Meanwhile, Namdeb said the long-term dynamics of the diamond industry would remain strong. There was likely to be demand growth in emerging markets, such as China and India, in future.

Title: Re: Namdeb shutting down production for a month
Post by: Leon Sumter on December 18, 2008, 06:55:35 PM
Mike, so we're talking about roughly 7000 Namdeb employees??
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on December 19, 2008, 04:00:14 AM
Nope, Namdeb has less than 2000 employees these days...

Title: Re: Namdeb shutting down production for a month
Post by: Leon Sumter on December 19, 2008, 02:42:38 PM
even a 1000 people is a big bunch of folk. I suppose a lot of folk would be near retirement?
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on December 19, 2008, 06:40:30 PM
I heard a worrying tale today, about some contractor workers not being paid by Namdeb...... reckons they would only be paid in February........ Anyone know anything?

Title: Re: Namdeb shutting down production for a month
Post by: Leon Sumter on December 19, 2008, 10:08:22 PM
Mike it looks like your 'Oranjemund Retirement Village' is coming closer now, what with all the houses that will soon become empty.
Title: Re: Namdeb shutting down production for a month
Post by: Keith Margetts on December 20, 2008, 01:25:12 AM
I'm really sorry to hear that the depression has reached so far and wide . . . all caused by some greedy fat-bastard USA banking executives, who should all be ferreted out, lined up against a wall, and shot!!  BoomSmilie_anim

Good luck to all the folks in my old home town . . . I wish you the best.

That Canadian Guy,
rooster
Title: Re: Namdeb shutting down production for a month
Post by: Leon Sumter on December 20, 2008, 07:07:37 AM
do not forget the consumers themselves who went on an orgy of spending on borrowed money and buying big gas guzzling 7 liter cars.
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on December 20, 2008, 08:33:27 AM
A horrible symbiosis  that   turned bad ..  and yes the rest of the world suffers cos when the big USof A  sneezes the whole world catches a cold ??  they should be left to  nurse their own illness ...  de link the  dollar from oil ...
Title: Re: Namdeb shutting down production for a month
Post by: Mike Stenson (RIP) on March 11, 2009, 03:20:22 PM
Namdeb is shutting down production for three months.........Was briefed by the MD this morning.  image031
Title: Re: Namdeb shutting down production for a month
Post by: Leon Sumter on March 11, 2009, 03:54:21 PM
jees now this is getting kind of serious guys.
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on March 11, 2009, 05:08:48 PM
Just gives us more time for Braai'.......... Stennie ... go round up a few more white horses.... I'll shoot some meat....

image061
Title: Re: Namdeb shutting down production for a month
Post by: Malcolm Bertoni on March 12, 2009, 07:45:47 AM
Here in Aus most of the factories, car manufacturers, etc, are working a 3 day week to keep things ticking over.  The mines here have also laid off thousands of workers. The government is pouring billions into the economy to keep unemployment down to a reasonable level - it stands at about 6-7% now, so still not desperate yet. We seems to be a bit protected from the worst of the recession, but it looks pretty bad. We have a strong social system so get something from the government to keep one going.  I dread to think what the unemployment rate will be like in SA/Namibia with very little gov support.

Tough times ahead for everyone.

Malcolm
Title: Re: Namdeb shutting down production for a month
Post by: Sean on March 12, 2009, 10:36:04 AM
Mike, this shutdown is obviously bad news for you.  How is Spar going to cope?
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on March 12, 2009, 10:54:37 AM
Well, 22 Workers have/are leaving us today......
We stocked 18000 lines, dropping it down to 11 000 lines...
We normally receive 3 lorry's a week from CPT, just spoke to Head Office, moving it to 1 lorry a week in 3 weeks time....

This is a global thing, all we can do is hang on for the ride.....
Title: Re: Namdeb shutting down production for a month
Post by: Alfred Boehme on March 12, 2009, 07:38:42 PM
I hear starting first April, 3 months production leave?


meanpuff
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on March 12, 2009, 08:39:21 PM
Perversely so ..   we just  had a  big meeting  this morning ... we are being asked to  supply  128 tons of  shrinkwrap for Savannah , & Hunters  variants for Distell  Gauteng  over a period of 3 and half months .. thats aside from the  70  plus for cape town ...  Ok  I see the same scenario as last year .. marketing predicted  huge  offtake and it slowed down to 60 % .. but so what ??? its work .. my dept still doing weekend work ...  and yes I'm going to have to pull the rabbbit out of the hat  to meet demand ... Ouch  but yes  $$$$ income for our company that garuantees jobs ..  the world is a strange place.. seems the worse things become  the more people drink ...  martini
Title: Re: Namdeb shutting down production for a month
Post by: SandyB on March 12, 2009, 08:48:53 PM
Awful part is  that i might in the light of all this have to delay my trip up  in april ... firstly all the long weekends  easter  and then the wisdom of our powers that be in declaring wed 22nd april  election day  IOW  a public holiday ?? ...  why could they not make election days on weekends  or a friday or a monday  ?? I know why  its a stupid populist move  or  a preverted wisdom ... if its on a weekend then the locals will be too pissed to get to the polling stations .. if its a friday they will  only have their minds on the weekend  .. and if  its a monday they will all be  too babelaas  ... I'm going to have to do  some fancy footwork and  bribing to get a skeleton crew to work  as i cannot  shut my process down for one day midweek Uuugh !! F.. g idiots     ape  ..  but yes I will see how things are going  and shape up ...
Title: Re: Namdeb shutting down production for a month
Post by: Michael Alexander on March 16, 2009, 09:02:13 AM
NAMDEB is taking a three-month 'production holiday' that will temporarily bring mining activity to a halt as the company grapples with the global financial crisis.

Namdeb's Group Manager for External and Corporate Affairs, Hilifa Mbako, told The Namibian on there had been no diamond sales in January and February, placing Namdeb's cash flow in a "unfavourable" position.
He said the 'production holiday' was the preferred option of several considered – one of which entailed shortening working days.
"The reason that the production holiday was the most favourable is because we save on the costs of inputs into production, such as fuel, which is the biggest cost, vehicles, electricity, and so on," he said.
Along with Managing Director Inge Zaamwani-Kamwi, Mbako last week toured the diamond area to discuss the impact of the global recession with employees and to weigh cost-saving options.
Asked how workers will be affected, Mbako told The Namibian that they will be paid their salaries during the production holiday.

"Also, not all areas will be shut down, and essential services such as the school, the hospital, the sea walls, etc [at Oranjemund] will continue to be run," he said.
Poliverster Hangula of the Mineworkers Union of Namibia (MUN) Oranjemund branch, who was present during the consultations, says only 260 of the mining giant's workers will remain active.
He confirmed that various options had been outlined, and that workers had been invited to say which they preferred.
The global financial crisis has left Namdeb deeply scarred, pulling down its income levels to below 50 per cent of the projected income for the period since September.
The company slowed down production significantly in December following dismal sales in November.
Mbako says the vessels did not return to the mining area in mid-February as planned, noting that "production levels are constantly being monitored and adjusted in response to demand".
Namdeb last month confirmed that it had renewed a N$650 million revolving overdraft facility, with the Namibian Government and DeBeers providing surety of N$325 million each.
Namdeb also embarked on a voluntary retrenchment exercise in January to cut its staff by at least 600.
Workers have until Monday to apply. About 578 employees have already applied and 520 applications have been approved. According to Namdeb, 279 have received their severance packages. Sixteen applications were turned down and decisions are still pending on the remaining 42.
Asked whether the response was strong enough to stave off forced layoffs, Mbako said: "We believe we will achieve the numbers and it appears that in the main we will have no forced retrenchments. However, there are a few positions where redeployment is unlikely and the incumbents have chosen not to accept voluntary separation. In such cases the company will have to consider retrenchment."
Responding to questions posed in the National Assembly on Thursday, Mines and Energy Minister Erkki Nghimtina described the diamond industry as having gone into survival mode.
"It is being predicted that the whole diamond pipeline from the mines to our factories up to jewellers will be in 'survival' mode for the rest of 2009 and for the most part of 2010," Nghimtina said, adding that serious job losses and possible closure of some diamond cutting and polishing factories can be expected.